What Happens on Granny Flat Delivery Day: A Step by Step Guide

Granny flat delivery day is the part everyone films. A truck pulls into the street, a crane sets up, and a finished home swings over the fence and settles onto its base. It is the visible end of the granny flat set up in a day approach, where the home is fitted out off site and then delivered, set up and fully fitted in one day rather than built in your backyard over months.

It looks effortless because the hard work happened earlier, in the factory and in your site preparation.

This guide walks through the day in order, so you know what to expect, who needs to be there, what you have to have ready, and what still has to happen after the crew drives away.

What granny flat delivery day actually covers

It helps to be clear about where the day starts and stops, because the phrase covers less than people assume.

Every home in our granny flat range arrives as one finished unit, so the day follows the same shape whatever model you choose. Delivery day covers transport of the home to your property, the crane lift, placing the home on your prepared base, levelling and securing it, and a walk through with you.

Delivery day does not cover:

  • Preparing the base, which is done well before
  • Connecting power, water and sewer or septic
  • Any approval process for your block
  • Landscaping, decks, steps or paths, unless arranged separately

You arrange your own licensed electrician and plumber to connect power, water and sewer. We can refer you to trades we have worked with.

So the honest picture is this. The home itself is on site and set up in a day. It is usually a short period after that, once your trades have been through, before anyone moves in.

What has to be ready before the truck arrives

Nothing derails a delivery faster than a site that is not ready. By the day before, all of this should be done and confirmed.

  • The base. Your concrete slab, piers or footings finished, cured and set out to the agreed position, to engineer advice.
  • Truck access. A clear, firm route in, wide enough, with cars moved off the street or driveway.
  • Crane access and reach. A stable, level spot for the crane to set up, with the lift path clear of powerlines, tree branches, awnings and roof edges.
  • Obstacles removed. Gates off hinges, low branches trimmed, bins, trampolines and pot plants moved.
  • Service points marked. Where power, water and sewer or septic will connect, so nothing is damaged.
  • Paperwork. Any approvals in place before the home is on the road. Our NSW granny flat approval guide covers what councils usually want.

If you are not sure your block clears these hurdles, send us photos and measurements first. It costs far less to find out early than to have a crane sitting idle in your street.

How granny flat delivery day usually runs

Stage Roughly when What happens
Arrival
Early morning
Truck and crew arrive, site walk
Crane set up
After arrival
Crane positioned, outriggers out, zone cleared
Rigging
Before the lift
Home secured to lifting gear, checks done
The lift
Mid morning
Home lifted over and lowered onto base
Levelling
After placement
Home levelled, packed and secured
Checks
Later in the day
Doors, windows, seals and fit out checked
Handover
Before crew leaves
Walk through, keys and documents

Early morning: arrival and the site walk

Crews start early, partly for traffic and partly because a lift is easier before the wind picks up. Expect the truck and the crane to arrive separately.

The first thing that happens is a walk of the site. The crew confirms the base position, checks the ground where the crane will stand, looks up for wires and branches, and agrees exactly where the home will sit and which way it will face.

This is your moment to speak up. Once the home is on the base, turning it or shifting it a metre is not a small job. Check:

  • Which wall faces the main house
  • Which side the entry door lands on
  • Where the service connection points come out
  • How much clearance you have for steps or a deck later

Somebody who can make decisions should be on site for this. It does not have to be you all day, but it should be someone who knows what you want.

The crane lift, step by step

The lift itself is usually the shortest part of the day, and the most controlled.

  1. Crane set up. The crane parks, extends its outriggers onto load spreading pads, and the operator confirms the reach and load.
  2. Exclusion zone. The area under and around the lift is cleared. Nobody stands under a suspended load, including you.
  3. Rigging. The home is attached to the lifting gear at its engineered lifting points, and everything is checked before any weight comes on.
  4. Test lift. The home is lifted slightly and held, to confirm balance.
  5. The travel. The home is lifted, swung over the house, fence or side boundary, and brought across the yard.
  6. Placement. Guided by the crew, the home is lowered slowly onto the base and positioned.

Neighbours will watch. It is worth giving them notice, especially if the street will be partly blocked or their driveway needs to stay clear.

Levelling, securing and the on site checks

Once the home is down, the crane is not released straight away. The crew checks the home is sitting correctly on the base before the weight fully transfers.

Then the careful work begins:

  • Levelling. The home is checked in both directions and packed or adjusted until it is true. This matters for doors, windows and drainage.
  • Securing. The home is fixed or tied down to the slab, piers or footings as required.
  • Function checks. Doors and windows opened and closed, locks tested, seals inspected.
  • Fit out check. Kitchen, bathroom, flooring, lighting and joinery checked for transport marks.
  • Clean up. Packaging, protective coverings and offcuts removed.

Walk around with the crew and look at the home yourself while they are still there. Note anything that bothers you in writing, with photos, on the day. Small things are far easier to sort out early than three weeks later.

Handover before the crew leaves

The last part of granny flat delivery day is the handover. It is short, but it is the part you will refer back to.

Expect to go through:

  • Where the electrical connection point and switchboard are
  • Where the water inlet and waste outlet are, and how they should be connected
  • How the hot water system and any appliances are set up
  • Where the documentation lives, including anything your electrician or plumber will need
  • Keys, and how the home should be locked up while it is unoccupied

Take photos of the connection points and the switchboard while everything is still exposed. Your trades will thank you.

If you have chosen our 57 m² Class 1a granny flat, the home is specified to meet Class 1a requirements, with the classification confirmed on site by an independent certifier. We work with an independent certifier for that step, and it happens separately from the delivery crew’s handover.

After the crew drives away

The home is on site and set up. It is not connected yet, and that is the next job.

You arrange your own licensed electrician and plumber to connect power, water and sewer or septic. We can refer you to trades we have worked with. Book them in advance so they arrive within days of delivery rather than weeks.

The usual order after delivery:

  1. Electrician connects the home to power and issues the compliance paperwork
  2. Plumber connects water, waste and the hot water system
  3. Any optional items go in, such as air conditioning, solar or a deck
  4. Steps or a landing to the entry door
  5. Final tidy of the ground around the home, so water runs away from it

Then it is furniture and moving day. If you want to see how the whole sequence fits together from order to move in, read our guide to granny flats set up in a day.

What can go wrong, and how to avoid it

Most delivery days are uneventful. The ones that are not usually trip over the same handful of things, and all of them are preventable.

  • Access that looked fine on the phone. Measure gates, driveways and turning space properly, and share photos early.
  • A base that is not right. Wrong position, wrong size or not cured. Follow the engineer’s advice and confirm the set out.
  • Overhead powerlines. These can change the crane size needed, or the whole approach. Flag them from the start.
  • Weather. Strong wind can stop a lift for safety reasons. Have a fallback date in mind.
  • Parked cars. Let neighbours know the date and the likely hours.
  • No decision maker on site. Orientation questions come up, and someone has to answer them.

Transport and crane costs vary with distance and difficulty, which is why they are quoted per site. Our post on delivery costs in NSW explains what drives the number. You can also talk to us about your block before you order.

Two-bedroom portable granny flat installed in a backyard in NSW
See what could land in your backyard

Compare sizes, layouts and prices across the relocatable granny flat range.

→ Browse our granny flat range · Call 02 5760 8582

Frequently Asked Questions

How long does granny flat delivery day take?

Most deliveries run within a single working day, starting early in the morning. The crane lift itself is often the quickest stage, while crane set up, levelling, securing and the final checks take up most of the time. A tight site, a long crane reach or awkward access will stretch the day out.

Someone who can make decisions should be on site, particularly at the start for the site walk and at the end for the handover. Orientation questions come up, such as which way the entry door faces, and they are hard to change once the home is on the base. If you cannot be there, nominate someone who knows exactly what you want.

The home is delivered, set up and fully fitted on the day, but it still needs services connected before anyone moves in. You arrange your own licensed electrician and plumber to connect power, water and sewer or septic, and we can refer you to trades we have worked with. Book them in advance so the gap after delivery is short.

This is why access is checked before you order rather than on the day. Crane size depends on the distance from where the crane can safely stand to where the home has to land, plus the weight of the home. Overhead powerlines, large trees and soft ground all affect it, so send photos and measurements early and we will tell you what your site needs.

Light rain rarely stops a delivery. Strong wind is the bigger issue, because a crane lift has safe operating limits and the operator will call it if conditions are unsafe. If the lift is postponed, it is rebooked, so keep a fallback date in mind and avoid scheduling the removalists for the same afternoon.