Granny Flat Site Preparation Checklist: What to Do Before Delivery

Good granny flat site preparation is the difference between a smooth delivery and an expensive false start. When a home is fitted out off site and then delivered and set up in a day, almost all of the effort shifts to what you do beforehand. The crane can only place the home where the ground, the access and the base allow.

The good news is that none of it is complicated. It is a list, and most of it can be done in a few weeks with the right trades.

This checklist walks through access, the base, services, drainage, paperwork and the final week, with the things people most often forget flagged along the way.

Why granny flat site preparation decides delivery day

A relocatable home arrives as one finished unit. That means it cannot be carried in piece by piece, squeezed through a side gate, or assembled around an obstacle. It has to be lifted in whole, and lowered onto something ready to take it.

So the questions are blunt:

  • Can the truck physically get to your property?
  • Can a crane set up somewhere stable and reach the spot?
  • Is there a level base of the right size, in the right place?
  • Are power, water and sewer or septic close enough to connect sensibly?
  • Will water run away from the home rather than under it?

If the answer to any of those is no, the fix almost always costs less before the home is ordered than after it is on a truck.

Start this process early. Send photos and measurements of your block to us when you are shortlisting models, not the week before delivery. It also shapes which model suits you, since a 13 m² studio and a 57 m² two bedroom home ask very different things of a site.

Access: getting the truck and the crane in

Access is the number one reason a delivery gets complicated, and it is the first thing to check.

For the truck, walk the route from the street to where it will park. Look at:

  • Street width, parking restrictions and turning space
  • Driveway width, gradient and any sharp turns
  • Kerbs, speed humps, bollards and street trees
  • Ground firmness, especially after rain

For the crane, it is about a stable place to stand and a clear path for the load:

  • A firm, level area for the crane and its outriggers
  • Reach from that point to where the home will sit
  • Overhead powerlines, which often decide everything
  • Tree branches, awnings, pergolas, roof edges and TV antennas
  • Underground services or tanks under where the crane will stand

Trim branches, take gates off hinges and move anything loose well before the day. If you are unsure, talk to us about your block and we will tell you what your site needs.

Choosing exactly where the home will sit

Once you know where a crane can reach, choose the position properly. This decision is easy now and difficult later.

Think about:

  • Sun. Which rooms get morning light, and which walls cop the afternoon heat.
  • Privacy. For the people in the home and for the main house, and for neighbours over the fence.
  • Distance to the main house. Short runs to services cost less, but too close can feel cramped.
  • Entry and paths. How someone walks to the door at night, in the rain, or with a walking frame.
  • Outdoor space. Room for a deck, a clothesline, a small garden or a parking spot.
  • Trees. Roots, falling limbs and leaf litter in gutters.

Mark the footprint out with pegs and string and live with it for a few days. Setbacks, easements and the space you must leave to boundaries vary by council, so confirm the position locally before you pour anything.

The base: slab, piers or footings

Every relocatable home needs a level base. Which type you use depends on your soil, your slope and the home you have chosen, and it should follow engineer advice rather than a rule of thumb from a forum.

A concrete slab gives a solid, continuous surface and a low floor height, which makes step-free entry easier. It costs more and takes longer to prepare and cure.

Piers raise the home on individual supports. They suit sloping blocks, reactive soils and sites where you would rather not remove much soil. They leave a gap underneath that needs skirting and ventilation thought.

Footings sit between the two, with pads or strip footings where the loads land.

Whichever you choose, get these right:

  • Size and position set out to the agreed dimensions
  • Level checked in both directions
  • Enough cure time before delivery day
  • Engineer advice for your specific soil classification

Budget for the base as a separate cost from the home. Our post on the costs people forget covers the ones that catch buyers out.

Granny flat site preparation checklist

Task Who does it When
Confirm truck and crane access
You with our team
Before you order
Check council requirements
You or a planning professional
Before you order
Mark out the position
You
Early planning
Engineer advice on the base
Engineer
Before base works
Pour slab or install piers
Concreter or builder
Weeks before delivery
Rough in service points
Electrician and plumber
Before delivery
Clear access and trim branches
You or an arborist
Week before delivery
Notify neighbours
You
Week before delivery

Services: power, water and sewer connection points

Your home arrives wired and plumbed internally. What it needs is somewhere to connect to, close by and ready.

You arrange your own licensed electrician and plumber to connect power, water and sewer. We can refer you to trades we have worked with.

Before delivery, get them on site to plan:

  • Power. Where the supply will run from, whether the main switchboard has capacity, and where the cable will come up at the home.
  • Water. Where the connection tees off, and whether the run needs trenching under a driveway or lawn.
  • Sewer or septic. Where the waste connects, and whether the fall works from the home’s outlet to the connection point.
  • Hot water. Where the unit sits and how it is supplied.

Trenches are far easier to dig before a home is sitting on the spot. Have your trades mark and, where practical, rough in the points while the yard is still open, then cap and protect them until after delivery.

Drainage and ground levels around the home

Drainage is the quiet one. It rarely stops a delivery, and it causes more long term grief than almost anything else on this list.

Aim for water to move away from the home on every side. Check after heavy rain, not on a dry day, because puddles tell you more than plans do.

Things worth sorting before the home lands:

  • Ground graded to fall away from the base
  • Downpipes from the main house not discharging toward the new home
  • A plan for the home’s own roof water, whether that is to a stormwater point or a tank
  • Agricultural drainage if the spot is naturally wet
  • Ventilation and access if the home sits on piers

Get these done while there is still open access for a bobcat or a mini excavator. Once the home is in position, even simple earthworks become a wheelbarrow job.

Paperwork, approvals and the neighbours

Sort the paperwork before you book anything that costs money by the hour.

Whether you need council approval depends on your council, your block, the size of the home and how it will be used. Relocatable homes can be treated differently from a fixed build in NSW, but the rules vary by council. Do not rely on what a neighbour did three years ago, and do not rely on a general article, including this one. Check with your local council or a planning professional before you buy. For the ACT, the rules are different, so check with the ACT planning authority.

Our NSW council approval guide for granny flats covers the usual questions and documents.

Neighbours are not paperwork, but they are worth the same care. Tell them the date, the likely hours and whether the street will be partly blocked. A crane over a shared fence is much easier when people know it is coming.

Your week-before checklist

In the last week, the list gets short and practical.

  1. Confirm the delivery date, arrival time and crane booking.
  2. Check the base is cured, clean and correctly set out.
  3. Clear the access route completely, including bins, bikes and pot plants.
  4. Take gates off hinges and trim any branches in the lift path.
  5. Move cars off the driveway and ask neighbours to keep the street clear.
  6. Confirm your electrician and plumber are booked for shortly after delivery.
  7. Decide the orientation of the home and write it down.
  8. Make sure someone who can make decisions will be on site.

That is the whole job. Get the access, the base, the services and the paperwork right, and delivery day is genuinely a one day event, which is the whole point of a home that is set up on site in a day. If you are still choosing a model, compare sizes in our granny flat range, look at the 37 m² two bedroom Cottage from $34,900, or download the price guide to plan your budget.

Two-bedroom portable granny flat installed in a backyard in NSW
Ready to plan your site

Send us photos of your block and we will tell you what preparation it needs.

→ Talk to us about your block · Call 02 5760 8582

Frequently Asked Questions

What does granny flat site preparation involve?

It covers four things: access for the truck and crane, a level base such as a slab, piers or footings, service connection points for power, water and sewer or septic, and drainage so water runs away from the home. Paperwork sits alongside all of it. Most sites can be prepared in a few weeks with the right trades.

Not always. A slab, piers or footings can all work, and the right choice depends on your soil, your slope and the home you have chosen. Follow engineer advice for your specific site rather than a general rule. Piers often suit sloping or reactive ground, while a slab gives a low floor height and easier step-free entry.

You need working room for the crane and crew on the day, plus ongoing space for paths, drainage, maintenance and any deck or steps. The distance you must leave to boundaries varies by council, so confirm setbacks and easements with your local council or a planning professional before you set the position. Mark the footprint out with pegs first.

You can do plenty of it, such as clearing access, moving obstacles, trimming branches and marking out the position. The base should follow engineer advice and be done by a suitable trade, and the service connections must be done by your own licensed electrician and plumber. We can refer you to trades we have worked with.

The delivery usually cannot go ahead, and rebooking a truck and crane costs money and time. The most common causes are a base that is not cured or correctly set out, blocked access, and overhead powerlines that were not flagged. Confirm everything in the week before, and send photos early if you are unsure about access.